Order Management
Order Management holds the whole purchasing process for a material: a request is opened, quotes are collected from suppliers, the quotes are compared side by side, one is approved, and the…
1. What it is for
Order Management holds the whole purchasing process for a material: a request is opened, quotes are collected from suppliers, the quotes are compared side by side, one is approved, and the approved quote opens a shipment card in Deliveries. As the goods arrive, the delivery rate is reflected back on this page.
The page answers these questions: what did we order, who quoted what, which job did we award, which order is past its due date and what did we save by negotiating.
An order or a quote is not a money movement — it is an intention and an agreement. Money only moves when the goods are received, and that record is written to Accounts by Inventory. So there is no account transfer on this page, and warehouse stock does not change from here either.
2. How to open it, who can see it
In the sidebar: Logistics & Materials › Order Management.
| Your permission | What you can do |
|---|---|
| View | You see the list, the summary band, the chart, the breakdowns and the quote panel. You can take the Excel, PDF and purchase-order exports and open quote documents and save them to your computer. New order, adding quotes, approval, revision, cancelling, closing and deleting are not drawn at all |
| Edit | Everything above, plus you add and edit orders and quotes, approve quotes, revise them, close, cancel and delete orders |
| No permission | The module appears dimmed and locked in the menu |
3. Anatomy of the screen

From top to bottom the page has four layers and follows the same order as Concrete Tracking, Equipment Tracking and Inventory: first you narrow down, then you read the result as numbers, then you look at its breakdown, and finally you go down to the rows. There is a fifth layer where the real work of the page is done: the quote panel that opens when you click a row.
| Layer | What it does |
|---|---|
| Filter bar | Search, status, material, supplier, scope and request period |
| Order summary | Two main amounts, a chart of the last twelve months, four small measures |
| Breakdown | Stage distribution and supplier distribution |
| Order list | A table grouped by the stage of the process |
| Quote panel | One order's key facts, actions and quote comparison |
All four of the first layers are drawn from the rows that pass the filter above. When you make a selection, all four change at the same time and no request goes to the server — the project data came down once.
Title and actions. The title reads Order Management with the description "Material orders, quote comparison and the approval process". On the right there are four buttons: Refresh, Download PDF, Download Excel and (if you have permission) New order.
Filter bar

It has two rows. The top row has the Search orders box, next to it the Filter by label with the Status, Material and Supplier filters, and at the far right the Scope switch. The bottom row has the Request period label with three preset ranges and two date boxes.
| Control | What it does |
|---|---|
| Search orders | Searches the material name, the description, the category, the status name and the supplier names on the quotes |
| Status | Narrows by status. The list is not alphabetical but in process order: Draft · RFQ sent · PO issued · Completed · Cancelled. Only the statuses that pass the current scope appear in the menu |
| Material | Narrows by material |
| Supplier | Narrows by company. At the end of the list there is a No quotes yet option — it brings up the orders that have received no quotes |
| Scope | A three-step switch: Active, Overdue, All. Each shows in brackets how many orders it holds |
| Current month · Last month · Current year | Preset ranges. The selected one is highlighted; pressing it again removes the range |
| Start · End | A free request-date range. If one is left empty there is no limit in that direction |
The page opens with the Active scope: completed and cancelled orders are not in the list. What you look for day to day is the open work; switch to All to see the closed ones.
While a filter is active, a clear button appears in the bar. If you have only typed in the search box it reads Clear search; if you have also picked a filter, a scope or a date it reads Clear filters and shows how many criteria are active. Clearing also resets the scope — but not to All: it returns to Active, the state the page opens in.

The filter menus feed each other: when you pick a status, the numbers in the material and supplier menus are recalculated for that status. So you can see whether ticking a second box will return anything before you tick it. The bracketed numbers on the Scope switch are likewise calculated against the material and status selection.
Order summary

Two amounts sit one above the other on the left of the card:
| Measure | What it shows |
|---|---|
| POs Issued | The total of approved quotes, excluding tax. Cancelled orders are not included |
| Awaiting Approval | The value of open, not yet approved orders based on their cheapest quote |
Awaiting Approval is not an estimate, it is a lower bound. If an average were taken, an expensive quote still waiting to be rejected would pull the expected cost up and the number would not support any decision. The line below the figure says how many open orders with no quotes at all are not included in this amount; if all of them have quotes, the description "Based on the cheapest quote for each open order" takes its place.
On the right there is a column chart of the last twelve months. The Chart measure switch at the top right offers three options: Amount (currency) (the value of POs issued), Orders (the number of orders opened) and Quotes (the number of quotes received).
Small measures are lined up below the card. Everyone sees the first three; the last two are project-wide financial totals and are drawn only for people with Financials view permission:
| Measure | What it shows |
|---|---|
| Open Orders | Orders that are neither completed nor cancelled. Below it, how many of them are drafts |
| RFQs Sent | Orders in the RFQ sent stage. Below it, how many have received no quotes at all |
| Overdue | Open orders past their due date. Above zero, the tile turns red |
| Savings vs Average Quote | On approved orders, the sum of the differences between the average of that order's priced quotes and the approved quote. If a quote above the average was chosen, that order counts as a minus. Below it, on how many orders it was calculated and the earlier measure, the difference vs the most expensive quote |
| Remaining vs Budget | The total of approved orders whose cost code is linked to a line in the project budget, taken from those codes' revised budget. If it is negative the tile is red. Below it, the number of cost codes, the budget and the order total. Not drawn if no order is linked |
Orders with a single quote do not count towards savings. No choice was made there: with one quote the "average", the "most expensive" and the "approved" are the same quote, and adding zero would make a negotiation that never happened look like a failed one. Revised quotes and quotes with no price entered are left out of the average; rejected ones are included.
The budget link is the cost code. If the order's cost code exists as a line in the budget, the order is linked; an order with no code, or in a code that has no budget, is left out of the comparison. The comparison counts orders only: concrete, plant and invoice costs in the same code are not here; the full picture is in the cost report under Financials.
Breakdown

There are two cards side by side and they do not ask the same question.
Stage distribution reads like a funnel: which stage the orders are waiting at. Each row holds the name of the stage, how many orders it has, its amount if any, and a share bar. The stages are in process order.
Supplier distribution shows who did what: each row holds the company name, how many quotes it gave, how many jobs it won and the total value of those jobs. The company with the most orders won is at the top. A company that has won nothing shows a dash rather than 0 ₺ in the amount column — so it does not read as "quoted for free".
Order list

Rows are grouped by status and the groups are laid out in process order. The group header shows the name of the stage, a red overdue badge if there is one, the number of orders and the total amount at that stage. Clicking a header collapses the group; the Collapse all button at the top right folds them all at once.
Inside a group the order is: first the overdue ones (the most overdue at the top), then those with an approaching due date, and last those with no due date entered.
| Column | What is in it |
|---|---|
| Material | The material name with the order's description below it. Clicking the name opens the quote panel |
| Requested | The requested quantity and its unit |
| Due date | The due date; if it has passed, a red N days late badge beside it. If it is not entered, No due date |
| Quotes | The number of quotes in the comparison, with lowest … below it |
| Approved | The approved quote's amount excluding tax, with the company name below it. A dash if there is no approval |
| Delivery | The delivery rate from the shipment cards, with delivered / expected quantity below. If there is no card, No shipments |
| Details | The button that opens the quote panel |
| Add quote | A plus button, drawn only with edit permission and only on draft orders and orders at RFQ stage |
You can sort by clicking the headers. Sorting uses the raw number; rows with no due date and rows with no approval fall to the end of the list.
Quote panel

Clicking a row or the Details button opens a wide window. Its title is the material name, with the quantity, the category and the description below it.
At the top of the window are the order's key facts: Requested, Due date, Request date and Stock in warehouse. The last field is there so that the decision "shall I order 60 tonnes" is made with the warehouse in view; if the material is at or below its reorder point, an orange Low stock badge appears next to it.
Below the key facts, up to three bands can appear depending on the situation:
- If the due date has passed, a red Past due date warning says how many days ago and what to do.
- If a shipment card has been opened, a delivery bar appears with the delivered / expected quantity and the number of shipment cards beside it.
- If there is more than one priced quote, a Quote range line puts the cheapest and the most expensive side by side, gives the Average quote next to them and shows the difference from the most expensive in a green badge. Once the order is approved, a second badge gives the savings against the average; if a quote above the average was chosen, the badge is orange and reads … above the average.
- If you have Financials view permission and the order's cost code is linked to a budget line, a Budget line gives the code's revised budget, the total of approved orders in that code and what remains (or the overspend).
- A PO no. line gives the order's number; once a quote has been approved, Approved by with the person and the time of approval appears next to it.
Then comes the action band: on the left the order's status badge, next to it (if available) Purchase order (PDF) and, if you have edit permission, New quote, Request quotes, Close order, Edit, Cancel order and Delete depending on the status.

At the bottom sits the quote comparison table, split into two groups:
- Quotes under evaluation — the pending ones, the approved one and the rejected ones. A rejected quote stays in this group, because the answer to "why was this company chosen" is the prices that were rejected.
- Revision history — old prices superseded by their own revision. The group header says superseded, the rows are dimmed and the difference columns are empty.
| Column | What is in it |
|---|---|
| Supplier | The company name, a Rev. N badge if any, with notes and (in the revision history) the reason for revision below |
| Unit price | The unit price excluding tax and the order's unit |
| Amount (excl. tax) | Unit price × requested quantity. Below it, an incl. 20% tax line; if there is no tax, No tax |
| Vs. lowest | A green Lowest quote badge on the cheapest, +amount and +percentage on the others |
| Valid until | The validity date; on a pending quote whose date has passed, an orange Expired badge. If there is no date, No expiry |
| Status | The quote's status badge, a blue Admin approval required badge when the approval limit is on and a pending quote is above it, and a paperclip button that opens the document if one is attached |
| Actions | On a pending quote Approve, edit and delete; on the approved quote Revise. On a quote above the limit, Approve is drawn only for a company administrator |
A quote with no price entered shows No price entered rather than 0.00 ₺ in the amount column — so it does not read as "quoted for free".
4. Fields
Order fields
| Field | What it means | Required |
|---|---|---|
| Material | The material definition the order is linked to. The list comes from the project's materials | Yes |
| Requested quantity | How many units are wanted. Use a comma or a full stop for decimals; do not type a thousands separator | Yes, greater than zero |
| Unit | The unit of measure. It fills in automatically when the material is picked and can be changed by hand | No |
| Due date | The day the material must be on site. Once it passes, the order is marked Overdue | No |
| Description / specification | The nature of the material and where it is going — C30/37, pump included — Building A foundation | No |
| Delivery address | Where the material is to be delivered. If left blank, the project location is printed on the purchase order | No |
| Payment terms | For example 30 days after delivery. Printed under Terms on the purchase order | No |
| Delivery terms | For example Delivered to site, unloading included. Printed on the purchase order | No |
| Notes to the supplier | Printed under NOTES on the purchase order | No |
| PO no. | Assigned by the server: prefix, year and sequence, for example PO-2026-0001. It cannot be changed | — |
| Request date | The day the record was opened. The app writes it; it cannot be changed | — |
| Status | Draft · RFQ sent · PO issued · Completed · Cancelled | — |
Quote fields
| Field | What it means | Required |
|---|---|---|
| Registered supplier | A choice from the companies defined in the project. Selecting is optional | No |
| Supplier name | The company's name. You can type a company that is not in the list here | Yes |
| Unit price | The unit price excluding tax. The label also shows the order's unit: Unit price (currency/t) | Yes, greater than zero |
| Add tax · Tax rate (%) | Unticked on a new quote. Ticking it opens the rate box, filled with the company's tax rate (20% unless another rate is set in Settings). The rate is limited to 0–100 and may have decimals | No |
| Quote date | The day the quote was given. Opens as today | Yes |
| Validity date | The day until which the price stands. It cannot be earlier than the quote date | No |
| Reason for revision | Appears only in revision mode. Whether the price, the due date or the terms changed | Yes, in a revision |
| Notes / terms | Terms such as delivery and payment. They also go onto the purchase order | No |
| Quote document | The PDF or photo the supplier sent. One document, up to 5 MB | No |
In the middle of the form there is a live total box with three lines: Amount (excl. tax) (with the quantity × unit price calculation next to it), Tax and Grand total. It changes as you type.
5. Step by step
Opening a new order

- Press the New order button at the top right.
- Pick a Material. The moment you do, that material's stock in the warehouse is shown at the bottom of the form; if it is at or below the reorder point, the band turns orange.
- Enter the Requested quantity; the Unit is copied from the material, change it if needed.
- Add a Due date and a Description if you want. In the Purchase order terms section at the bottom of the form you can enter a delivery address, payment and delivery terms and notes to the supplier; all of them are optional and none of them changes any amounts.
- There are two ways to save:
- Create draft — the order stays as a draft. When the first quote is added it moves to the RFQ sent stage automatically.
- Create and request quotes — the order opens directly in the RFQ sent stage.
Adding a quote

- Press the + button on the order's row, or New quote in the panel.
- If the company is registered in the project, pick it from the Registered supplier list; the name is copied into the box. If it is not registered, type it straight into the Supplier name box.
- Enter the Unit price excluding tax. If there is tax, tick Add tax and write the rate.
- The Quote date comes in as today; correct it if the supplier gave the quote earlier. If you enter a Validity date, the quote is flagged in the list once that date passes.
- Attach the Quote document if there is one and press Save.
Editing and deleting a quote
A pending quote can be edited directly: press the pencil button at the end of its row in the comparison table. The way to change the price of an approved quote is not editing but a revision.
The bin button deletes the quote permanently, along with its document if there is one. On rejected and revised quotes these buttons are not drawn — they are the record of the purchasing history and are not changed.
Approving a quote

- Press the Approve button on the row of the pending quote you have chosen in the comparison table.
- The window that opens names the company and the amount excluding tax, and explains below what will happen after approval. If the quote's validity has expired, a second warning appears as well.
- Press Approve.
The approval does four things at once: the other pending quotes are rejected, the chosen quote is approved, the order moves to PO issued and a shipment card is opened in Deliveries. The rest of the shipment card's life — on the way, received, delivery ticket — is that page's job.
The person who approved and the time of approval are saved with the order; they appear in the panel and in the signature area of the purchase order. If the approval is undone and the quote revised, this is cleared and written again on the next approval.
Approval limit. If an administrator has set an amount on the Settings › Order approval limit card, only a company administrator can approve a quote whose amount excluding tax is above that limit. Such a quote has an Admin approval required badge in its status column, and the Approve button is not drawn for anyone who is not an administrator. Quotes at or below the limit are approved as before by anyone who can edit Order Management. The rule is also enforced on the server: if the limit changed while you were on the page, the approval stops with Only a company administrator can approve a quote of this amount and no quote is changed. Raising the quantity of an approved order, or the price of an approved quote, so that the amount goes above the limit is likewise open only to an administrator. While the limit is off (the default), approval works as before.
Revising an approved quote

When the supplier changes the price or the terms, use the Revise button on the approved quote's row. The window says before you save what will happen:
- The order's approval is withdrawn.
- Any shipment cards are cancelled and archived.
- The old quote is closed as Revised and the reason for revision you write is recorded on it.
- The new quote is added to the chain as Rev. N, in pending state.
- The order returns to the RFQ sent stage.
Editing an order
The Edit button in the panel changes the order's quantity, unit, due date and description. The material can be changed too.
Orders with several items
Add item on the order form puts more than one material on an order (the button appears when the server supports it). The cost code, required date and terms apply to the whole order. In the list the row reads 3 items: Rebar, Cement, Sand. On the quote form each item gets its own unit price; a quote with a missing price can't be approved. An order goes to one supplier: to buy an item from another company, use Move items to a new order in the panel to put the selected items on a new order with the same required date, code and terms. The move happens in one step; every quote that priced a moved item comes to the new order with the same supplier, price, dates, note and attachment as a pending quote. You approve it on the new order.
With two or more quotes the panel shows an Item comparison table: items in rows, quotes in columns, the unit price and line amount in each cell. The lowest price of each item is marked; a cell without a price shows "—". Below are the quote totals (excluding and including tax) and the number of unpriced items. Prices from an incomplete quote are shown but don't count towards the lowest price. When buying items from different companies is cheaper, a suggestion appears under the table: Cheapest item by item: ₺285,250.00, ₺3,000.00 less than the B quote. The Move to a new order button next to it puts the item whose lowest price is elsewhere on a separate order in one step. The suggestion is for information only and isn't added to any total.
Preparing a request for quote (RFQ)
Before approval the panel has a Request for quote button. In the window you can pick a supplier (or leave it empty to send the same text to several companies) and enter a quote deadline; the date goes on the document only and isn't saved. The document carries the company address and logo (Settings → Purchase order document), the order number as a reference, the items without prices (material, quantity, unit, description), the required date, the delivery address and the terms. Save the file with Download PDF, or use Copy text and paste the email text into your own email; the app doesn't send email. If the selected company has an email address on file, a To line and a Copy address button appear. The document and the text are in the app's language.
On approval each item gets its own shipment card. On an approved order only quantities can change; to add or remove items, revise the quote. The purchase order and the Excel export list every item on its own line.
Material requests
If the server supports it, an Orders | Requests switch appears at the top of the page. Needs on site are entered here as requests: use New request to enter the needed-by date, where the material is used, a note and the items (material, quantity, description), then Save draft or Save and submit. Anyone who can view Orders in the project can make a request; the person who made the draft edits, submits, cancels or deletes it.
Someone who can edit orders opens a submitted request, picks items with Convert to order and creates a single order (one item gives a single-item order). Example: the site chief asks for 10 t of rebar and 200 bags of cement; purchasing converts both into one order, or converts only the rebar and leaves the cement for later. The request then shows as Partly ordered; the remaining item is converted later or rejected with Reject and a reason. The Order PO-… link next to an item opens the order; in the order panel the Items from requests box shows the request. If the order is deleted or cancelled, the item can be converted again.
Closing an order
On an order in the PO issued state, a Close order button appears in the panel. It is used when the job is done: the order is marked Completed, shipment cards with nothing received are cancelled, and partly received ones are closed as delivered.
Cancelling an order
Every order that is not closed has a Cancel order button. The order is marked Cancelled and stays in the list — it is not deleted.
Deleting an order
The delete button is drawn only on orders with no shipment card opened. The confirmation window says that the quotes on the order and their documents will be deleted too.
On an order with a shipment card, the delete button does not appear at all: the owner of that chain is the Deliveries page, and deleting a shipment also touches stock quantities and the account ledger. Rather than removing the record from the list, cancel it.
Opening a quote document
The paperclip button next to the status badge in the comparison table opens the document the supplier sent in a viewer. You can save it to your computer from there. Viewing does not require edit permission.
Taking a purchase order
In the panel, orders with an approved quote show a Purchase order (PDF) button. That is the document sent to the supplier; details are below.
6. Exports
There are three exports. Two of them send out the list you see on screen — whatever the filter is, that is what goes into the file; the third describes a single order and is taken from the quote panel.
If the save dialog is closed, nothing happens; once saved, a band appears at the top of the page showing the full path of the file. All three exports can be taken with view permission.
Download Excel
The file name starts with Order_Report_ and has a date–time stamp added to the end. The workbook has three sheets; the first two answer two different questions. The third sheet, Order items, lists every item on its own line (PO no., material, quantity, approved unit price, tax rate, amount), with a subtotal, one line per tax rate and the grand total below.
The Orders sheet carries fourteen columns: Material · Category · Requested · Unit · Request Date · Due Date · Delay (days) · Status · Quotes · Lowest (currency) · Approved Supplier · Approved Amount (currency) · Delivered (%) · Description.
The Quotes sheet writes all the quotes of the orders that pass the same filter, eliminated ones included, in thirteen columns: Material · Supplier · Quote Date · Valid Until · Unit Price (currency) · Amount (currency) · Tax (%) · Tax Amount (currency) · Grand Total (currency) · Difference to Lowest (currency) · Revision · Status · Notes. The reason for revision is appended to the notes as Revised: ….
Both sheets have a three-line header block at the top: the project name; the report date and the totals; and a one-line summary of the filter applied. That last line matters — it is written so that a file taken with one status selected is not mistaken for the whole project when it is emailed on. If there are overdue orders, their number goes into the header block too. If you have Financials view permission, the header also gives the savings vs average quote, the negotiation savings (vs the most expensive quote) and, when orders are linked, an against budget line (budget, orders, remaining).
Three useful details: the header row is frozen; the filter is on; and the dates and all figures are real cell values — they can be sorted, summed and pivoted. The amount cell of the lowest quote is written in bold green.
The last row of the Orders sheet is GRAND TOTAL; the quote count and the approved amount are summed. The Requested column is not summed and a dash stands in its place: a project may hold tonnes and pieces side by side. On the Quotes sheet the TOTAL row sums the amount and the grand total.
Download PDF
An A4 landscape status report with nine columns: Material · Requested · Due Date · Status · Quotes · Lowest (currency) · Approved Supplier · Amount (currency) · Delivered.
The first page carries the project name, the Order Status Report title, the time it was produced and the filter summary; at the top right it shows the approved total, the order and quote counts, and warnings about overdue orders and orders with no quotes if there are any. From the second page on, a thin band is repeated at the top, the column headers are written again on every page, and the page number is at the bottom.
The delay is written in orange below the due date rather than in a separate column. The delivery rate is shown as a percentage, not as a bar.
The last row is GRAND TOTAL: the quote count and the approved amount are summed. The Lowest column is not summed — adding up the cheapest quotes of different orders would produce a "total" of which none was ever approved.
Purchase order (PDF)
This is the document sent to the supplier and it is taken from the quote panel, only on orders that have an approved quote. The file name is made up of Purchase_Order_, the material name and the PO number.
It is a single portrait page in the company's paper size (A4 or Letter) and carries:
- The company logo (if one has been uploaded in Settings), the PURCHASE ORDER title, the project name, the PO No., the time of issue and the request date.
- Two parties: ORDERED BY (the company name, address and project; the project name if no company name has been set) and SUPPLIER (the company on the approved quote, the quote date and the revision number if any).
- The line-item table: the material and its description, quantity, unit, unit price, amount; below it Subtotal (excl. tax), Tax (…%) and Grand total. On an order with several items each item is a line; if the tax rates differ, each rate gets its own line with its base.
- TERMS: the delivery address (the project location if blank), payment and delivery terms, the delivery due date, the quote validity and the quote's notes. If there are none, the heading is not drawn either.
- NOTES: the notes to the supplier written on the order, if any.
- Two signature areas: Prepared by / Stamp · Signature and Approved by · Signature; when the approver is known, their name and the time of approval appear under the label.
7. Things worth knowing
All money totals on screen exclude tax. Tax is not the project's cost but the state's share, and the amount of the same goods is read excluding tax in Inventory and Concrete Tracking too. Tax is not lost: it is written below the row in the quote comparison, on its own line in the purchase order, and in its own column on the Excel Quotes sheet.
A quote's amount is calculated from the unit price. Unit price × requested quantity. That way every quote answers the same question even when the quantity changes: "what is this company charging per tonne". The stored total is only used for quotes with no price entered at all.
The lowest quote is chosen by price. An approved quote may be more expensive than a pending one; in that case the Lowest quote badge sits not on the approved row but on the one that really is the cheapest.
Rejected quotes stay in the comparison. When an order is approved the others are rejected, but they do not drop off the list. A rejected quote is the justification for the choice; without them the fact that "three companies were asked" would be lost. Only the revision history moves to a separate group.
The validity warning appears only on a pending quote. Whether a rejected or approved quote has expired changes nothing; the badge would be noise there. The validity day is inclusive: a quote valid until 15 March is still valid on 15 March.
Delay is only calculated on an open order. A completed or cancelled order may be past its due date, but no badge appears — that would show a closed job as if it were still open.
The delivery rate comes from the shipment cards. Archived cards are not counted; if there is no card at all, the cell reads No shipments — which is not the same as "0% delivered". The bar stops at 100%; if more than expected has been received, read the real figures from the delivered / expected line under the bar.
This page does not write to the account ledger. An order and a quote are an agreement; the entry in the supplier's ledger is written by Inventory when the goods are received.
Search respects Turkish letters. Typing santiye finds Şantiye Kablosu, and oznur finds Öznur Kablo. Search works on the status name too: typing PO issued brings up the orders at that stage.
When you pick a date range, records with no request date drop out of the list. They are not lost; they come back when you clear the filter.
Unit names are the values you typed. The common units are shown in the interface language — ton as t, adet as pcs; any other unit (m²) appears exactly as it was written. The material names, descriptions and notes in the screenshots above are likewise data and stay in the language they were entered in.
8. Related chapters
- Inventory — the material definitions an order is linked to are created there. The order window and the purchase order show that material's current stock in the warehouse. The movement that increases stock when goods are received is created there too.
- Deliveries — the shipment card opened when a quote is approved lands there. Receiving, delivery tickets and the goods-acceptance record are that page's job; the Delivery column here shows its result.
- Suppliers — the companies that give quotes are defined there. A company that is not in the list can also be typed as free text.
- Accounts — this page does not write to the ledger; the entry in a supplier's account is made by Inventory when the goods are received.
- Financials — the project's material cost is totalled there together with the other cost items.